

MEC Priority ProjectThe MEC for Housing has identified a number of priority housing projects, which have been established to facilitate accelerated housing delivery within Gauteng Province. There are six (6) essential services projects and one (1) social housing project, namely: Essential Services:
Rental Housing:
OlievenhoutboschThe MEC for Housing identified and listed a number of priority housing projects for accelerated delivery of which Olievenhoutbos Ext. 21 & 23 (G02060001) and Ext. 24 & 25 (G03030046) and Ext. 26 in Tshwane is one. On the 27th of January 2004, the Department signed an agreement with GAMONT DEVELOPMENT for the construction of 2,905 top structures in Olievenhoutbos Ext. 21 & 23, Ext. 24 & 25 and Ext. 26. This project has three phases:
Unforeseen factors, seriously impacted upon attainment of these dates. The unavailability of water for construction purposes delayed work, whilst heavy rains also affected construction. Current project status (phase 1) is as follows:
In summary, the developer had completed 225 of the targeted 500 units as at 31 March 2004. At the current building rate the outstanding Phase 1 structures amounting to 275 will be completed by mid April 2004. Budgetary allocations were as follows:
Heidelberg Ext 23 (G94060013)HAC has provided approval to proceed with Phase 2 of the project, consisting of 2003 units. On the 7th of January 2004, the Department signed an agreement with Grinaker LTA Ltd for the construction of 2503 top structures in Heidelberg Ext. 23, to be completed in two phases:
Completion of phase 1 of the project overran due to the following constraints:
Overall twenty six (26) working days were lost as a result of the delays highlighted. Current project status (phase 1) is as follows:
In summary, the developer had completed 227 of the targeted 500 units as at 31 March 2004. At the current building rate of sixteen (16) top structures per day the outstanding Phase 1 structures amounting to 273 will be completed by 30 April 2004. Budgetary allocations were as follows:
Construction delays will cause a revision of the 2004/5 budget to R39 349 764, i.e. an increase of R4 719 897.
Palm RidgeHAC has provided approval to proceed with the construction of top structures by the Local Authority for the Palm Ridge (G98120399) project on 14 January 2004. The total project consists of 10 000 units. Ekurhuleni Metropolitan Council selected to proceed as implementing agent for the construction of houses on the Palm Ridge project and in-principle approval has been granted for this approach. The project will be completed in two phases:
Budgetary allocations were as follows:
Construction delays will cause a revision of the 2004/5 budget to R39 349 764, i.e. an increase of R4 719 897.
Palm RidgeHAC has provided approval to proceed with the construction of top structures by the Local Authority for the Palm Ridge (G98120399) project on 14 January 2004. The total project consists of 10 000 units. Ekurhuleni Metropolitan Council selected to proceed as implementing agent for the construction of houses on the Palm Ridge project and in-principle approval has been granted for this approach. The project will be completed in two phases:
Budgetary allocations were as follows:
JohandeoSeakay Engineering Services were appointed developers to the project on 26 January 2004. Johandeo, within the Umfuleni Local Municipality jurisdiction, is a two-phase project consisting of:
Progress on Phase 1, behind schedule as at 31 March 2004, was as follows:
Budgetary allocations were as follows:
An addendum to the developer's contract for the construction of an additional 597 units (Phase 2) has been approved. The total budget allocation has been increased, correspondingly, from R25 527 548 to R27 281 211.
Mogale City: (G94060076): Sinqobile, (98120350): Munsieville Ext. 4, Kagiso Ext. 12, Rietvallei Proper and Rietvallei Ext. 1HAC has provided approval to proceed with the construction of top structures by the Local Authority for the Mogale City projects on 5 December 2003. The total project consists of 5 601 units. Mogale City selected to proceed as implementing agent for the construction of houses on the abovementioned projects and in-principle approval has been granted for this approach. The project will be completed in two phases:
* The total project comprises of 2 146 units. 1 646 units will be completed in phases 1 and 2 and 500 units will be made available to the Peoples Housing Process programme. ** The total project comprise of 3 029 units. 2 529 units will be completed in phases 1 and 2 and 500 units will be made available to the People's Housing Process programme. Budgetary allocations were as follows:
Golden TriangleThe City of Johannesburg (COJ) has been appointed as implementing agents, in terms of an agreement entered in terms of Chapter 3A of the National Housing Code. The Department and the Developer entered into an agreement on 22 November 2003 in respect of 5 330 Project Linked Subsidies for the installation of services and construction of toilet structures on the Property. The total budgetary cost of the project has been determined as R135 797 740, as follows:
KersiesdorpKersiesdorp, a multiple phased project, has been allocated a R18 million budget. The project aims to improve the infrastructure and maintenance of the units. As at 31 March 2004, Phase 1 (paving, landscaping, palisade fencing, electrification) has been completed at an approximate cost of R7m. |